Beddawi combined cycle P.S. 3*150 MW - Tripoli - Lebanon

 
 Owner  Electricity of Lebanon (EDL).  
 General Contractor  Ansaldo – Energia.  
 Location  Tripoli - Lebanon.  
 Project Period  October 1996– May 1998.  
 Scope of Work  - Unit and inter bus Transformers assembly.
 - Unit transformers main Insulated bus duct erection.
 - 66 KV switchgear erection including cabling.
 - Metal clad 20 KV switchgear erection.
 - 220 & 66 KV Cable pulling and termination assistance.
 - Erection of the plant raceways in Boiler , Turbine and plant.